October 3 – October 7, 2022:
Bannock Drive
- Completion of all sanitary sewer, water and storm utilities
- Begin road rough grading work for later sub-base installation
Poncho Road
- Completion of the water main, hydrants, vaults and valve installation
- Begin storm line, inlet, and manhole installation
The contractor will move another crew to Poncho Rd next week to assist in expediting the completion of the utility work.
Week of Oct. 10, 2022: Contractor anticipates to install the tap of the Poncho Rd water main and begin testing per the water districts requirements. This testing may take up to five (5) days to complete. Also during this time period, the contractor hopes to be able to connect the new sanitary sewer main to the existing facilities.